8th Dec 2016 sagbadai community center

Thursday 1st D + 17: Construction of the Community Center ...
When we arrived in Togo a fortnight ago, we hoped to find a more advanced building under construction, given the budget available. The organizational difficulties encountered by our partners have since been corrected and we have re-launched the project in order to consolidate the objective: a building finished in November 2017, in such a way that we may concentrate on domestic equipment in the final year of the project, as planned.
We have designed a complete set of plans with a local partner in order to restart construction with the contractor as soon as possible and facilitate exchanges between project partners. A big thanks to Vincent de Granite Construction for his help ...