New building for the Sokodé High School

28th Jan 2022 highschool children

Flagship project funded by SPESS for 2022, the construction of the new 2-class building for the Lybama high school in Sokodé (Bamabodolo district) has begun.
First step, making bricks (blocks) on the ground, with cement, sand and water. With a bag of cement of 50 kg, one manufactures 30 hollow bricks (40X20), using moulds. With one ton, it is therefore 600 bricks, which will be left to dry and wait, before passing into the expert hands of the masons for the elevation of the walls (48 m2 of walls for one ton of cement).
For your information, a 50 kg bag of cement costs 4,200 CFA Francs (6.50 Euros), or about twice the daily wage of a Togolese worker...